All permits require a permit application to be filled out, which includes a description of the project and a list of contractors that will be working on the project.
-
All contractors listed must be registered and/or licensed with the City of Darien.
-
Most permits require you to bring in your plat of survey. You will be requested to have your structure – such as a deck, shed, pool, etc... drawn to scale on a copy of your plat of survey.
-
Many permits require architect stamped plans along with the permit application, including: All new residential and commercial buildings, additions, alterations, sunrooms, etc…
-
Simple permits, such as: fence, roof, electrical service upgrade, driveway replacement, etc… can usually be issued immediately. *Please note: if your property is located in flood plain the permit process will take considerably longer.
-
All other permits are required to go thru a zoning and/or plan review process. This process takes approximately two to four weeks from time you submit your application. *Please note: if your property is located in flood plain the permit process will take considerably longer.
-
The permit fee schedule can be found on our website.
-
Permit and plan review fees are not collected until the permit process is complete and the permit is issued. Fees may be paid by cash or check only.
-
Most permits require inspections to take place. You will be given a sheet of required inspections when the permit is issued. All inspections must be scheduled by 2:00pm the day before you require the inspection.
For more detailed instructions, please see the Building Permit Information Packet.
You may contact the Community Development Department at 630-353-8115 or via e mail mbelmonte@darienil.gov for question concerning the application process.