AGENDA MEMO
City Council
April
16, 2012
Issue Statement
Approval of the 2012 Street Maintenance contract with
James D. Fiala Paving Inc. in the amounts of $1,253,108.49 for the base bid;
and Option
No 1-Resurfacing Public Works
Facility $174,849.30; and Option No 2-Darien Pathway Development $23,557.10;
and Option No 3-Capra Trail-Bailey Park Homeowners Association $66,191.90; and
Option No 4-Mark Delay School Parking Lot $63,411.60 and Option No 5-Selective
Base Repair 1,500 Square yards $74,250.00 for a grand total cost of $1,655,368.39.
Background/History
The City’s 2012 Street Maintenance Program includes 4.9
miles. The program consists of the following roads:
|
2012 ROAD
RESURFACING PROGRAM |
|||||
|
STREET |
SUBDIVISION |
LIMIT |
RATING |
LAST
REHAB |
ROAD
LENGTH |
|
Poplar Lane |
Marion Hills South |
Janet Avenue to Elm Street |
53 |
1999 |
840 |
|
Maple Lane |
Hinsbrook |
Richmond Ave to Clarendon Hills
Rd |
61 |
1997 |
2840 |
|
Donegal Drive |
Carriage Hill |
Meyers Wood Park to Donegal
Court |
62 |
1995 |
1254 |
|
Stewart Drive |
Bailey Park |
Bailey Road to limit |
63 |
1996 |
1400 |
|
Cramer Lane |
Farmingdale Village |
Brewer Road to Drover Lane |
64 |
1998 |
480 |
|
Tamarack Drive |
Hinsbrook |
Richmond Avenue to Beechnut
Lane |
64 |
1999 |
2200 |
|
High Road |
Marion Hills North |
67th Street to
Plainfield Road |
65 |
1998 |
2950 |
|
Arrow Lane |
Farmingdale Terrace |
Portsmouth Drive to limit |
65 |
1992 |
600 |
|
Comstock Lane |
Farmingdale Terrace West |
Walnut Drive to Nantucket Drive |
65 |
1995 |
900 |
|
Del Court |
Farmingdale Terrace West |
79th Street to limit |
65 |
1996 |
400 |
|
Bantry Court |
Darien Club |
Darien Club Drive to limit |
65 |
1996 |
660 |
|
Clover Court |
Darien Club |
Darien Club Drive to limit |
65 |
1995 |
350 |
|
Burgess Lane |
Farmingdale Village |
Drover Lane to limit |
65 |
1998 |
390 |
|
Pine Court |
Farmingdale South |
Greenbriar Lane to limit |
65 |
1998 |
600 |
|
High Road |
Marion Hills South |
Plainfield Road to Janet Avenue |
66 |
1998 |
440 |
|
Bentley Avenue |
Plainfield Highlands |
71st Street to 72nd
Street |
66 |
1998 |
480 |
|
Hayenga Lane |
Farmingdale Terrace West |
Walnut Drive to Andermann Lane |
66 |
1994 |
980 |
|
Allison Lane |
Farmingdale Unit 5 – 9 |
Cass Avenue to limit |
66 |
1989 |
335 |
|
Sandalwood Drive |
Farmingdale Village |
Beller Drive to Water Tower
Lane |
66 |
1987 |
600 |
|
Clare Court |
Darien Club |
Darien Club Drive to limit |
67 |
1996 |
360 |
|
Irish Court |
Darien Club |
Darien Club Drive to limit |
67 |
1995 |
350 |
|
Exner Court |
Farmingdale Unit 5 – 9 |
Exner Road to limit |
67 |
1994 |
160 |
|
Maple Lane CDS #1 |
Hinsbrook |
Maple Lane to limit |
67 |
1997 |
180 |
|
Andermann Lane |
Farmingdale Terrace West |
Hayenga Lane to Nantucket Drive |
68 |
1994 |
660 |
|
Baker Court |
Farmingdale Terrace West |
Andermann Lane to limit |
68 |
1996 |
640 |
|
Water Tower Lane |
Farmingdale Village |
Pearson Drive to Sandalwood
Drive |
68 |
1996 |
340 |
|
Maple Lane CDS#2 |
Hinsbrook |
Maple Lane to limit |
68 |
1997 |
180 |
|
Alden Lane |
Farmingdale Village |
Brewer Road to Burgess Lane |
69 |
1998 |
760 |
|
Barrymore Drive |
Bailey Park |
Bailey Road to Capra Trail |
69 |
1996 |
1500 |
|
2012 ROAD
RESURFACING PROGRAM |
|||||
|
STREET |
SUB
DIVISION |
LIMIT |
RATING |
LAST
REHAB |
ROAD
LENGTH |
|
|
|
|
|
|
|
|
Robert Road |
Carriage Hill |
Oldfield Road to Donegal Drive |
69 |
1995 |
820 |
|
Sleepy Hollow Lane |
Regency Grove |
Adams Street to Cass Avenue |
69 |
2000 |
1100 |
|
Shannon Court |
Carriage Hill |
Robert Road to limit |
70 |
1995 |
325 |
|
|
Totals |
Ln Feet |
|
|
25,974 |
|
|
|
Miles |
|
|
4.9 |
|
OPTIONS |
|
|
|
|
|
|
Public Works Parking Lot |
1041 S. Frontage Road |
|
|
|
|
|
Darien Pathway |
Darien Path |
Cass Avenue to limit |
|
|
|
|
Capra Trail |
Bailey Park |
Barrymore Drive to limit |
|
|
|
|
Mark DeLay School South Parking
Lot/Kelly Circle |
|
|
|
|
|
The bid tabulations included 5 additional options and
are broken down as follows:
Base Bid-Includes the proposed schedule as listed above “2012
Road Resurfacing Program” $1,253,108.49
Option No
1-Resurfacing Public Works Facility $174,849.30 - Included the removal and replacement of the bituminous
surface of the Public Works Facility parking lot at 1041 South Frontage Road.
Option No
2-Darien Pathway Development $23,557.10 - This item includes selective base repair and resurfacing for Darien
Pathway as part of the Public Improvements. The funding for the proposed
improvement is secured from the letter of credit on file and called by the City
Council on February 21, 2012.
Option No
3-Capra Trail-Bailey Park Homeowners Association $66,191.90 -See Attachment B - This item includes the removal and replacement of a
private roadway, Capra Trail located in the Bailey Park Subdivision. The scope of
work includes removal of the existing bituminous roadway, aggregate base
repair, and bituminous surface products. Funds for the project are required to
be on file with the City by March 2, 2012.
Option No
4-Mark DeLay School Parking Lot $63,411.60 - See Attachment C - This item includes selective removal and replacement of
the Mark DeLay parking lot as per the attachment. The scope of work includes
selective bituminous and aggregate base repair, and bituminous surface
products. The proposed work is further covered through an Intergovernmental
Agreement and under a separate agenda memo.
Option No
5-Selective Base Repair 1,500 Square yards $74,250.00 - See Attachment D – This item
includes selective roadways for 1,500 square yards of base repair on roads
outside the scope of the scheduled 2012 roadway resurfacing program. The base
repair was identified as a preventive maintenance program that would address
identified sections of roadways that require sooner than later repairs. This
maintenance item also preserves the roadways from more costly repairs in the
future. The identified sections are considered base repair patches and are
identified as sections of roadways that the existing asphalt is breaking apart
and/or developing severe alligatoring, rutting and potholes. The identified
deficiencies indicate that base is weakened and requires stabilization. The
identified areas are excavated 6-inches and replaced with a bituminous product.
Sealed bids were opened on February 1, 2012. A summary of the three (3) bids received is
attached as Attachment A. James D. Fiala
Paving provided the lowest competitive bid for the base bid and any addition of
the options.
The proposed 2012 Road
Program would be funded from the following FY 12-13 Budget:
|
ACCOUNT NUMBER |
ACCOUNT DESCRIPTION |
FY 12-13 BUDGET |
PROPOSED EXPENDITURE |
|
25-35-4855 |
STREET
RECONSTRUCTION/REHAB-2012 City Road Maintenance Program |
$ 1,253,108.49 |
$ 1,253,108.49 |
|
25-35-4855 |
OPTION 1-Public
Works Facility |
$ 174,849.30 |
$ 174,849.30 |
|
25-35-4855 |
OPTION 5-Base
Repair 1500 Square Yards |
$ 74,250.00 |
$ 74,250.00 |
|
TOTAL
CITY PROGRAM EXPENDITURE |
$ 1,502,207.79 |
$ 1,502,207.79 |
|
|
25-35-4855 |
REIMBURSEMENT-Option No 2-Darien Pathway
Development |
LETTER
OF CREDIT CALL (received) |
$ 23,557.10 |
|
25-35-4855 |
REIMBURSEMENT- Option No 3-Capra Trail-Bailey
Park Homeowners Association |
FUNDS
ON FILE |
$ 66,191.90 |
|
25-35-4855 |
REIMBURSEMENT- Option No 4-Mark DeLay School
Parking Lot/Kelly Circle |
IGA ON
FILE – to be invoiced upon completion |
$ 63,411.60
|
|
TOTAL
PROGRAM EXPENDITURE |
|
$ 1,502,207.79 |
$ 1,655,368.39 |
Committee Recommendation
The Municipal Services
Committee, Christopher B. Burke
Engineering and staff recommend awarding the base bid and Options 1-5 to James D.
Fiala Paving Inc. for the 2012 Road Maintenance Contract in the amount of
$1,655,368.39. James D. Fiala Paving
Inc. was awarded the street maintenance contracts in 2005, 2007, 2008, 2009,
2010 and 2011 and has provided quality results for the program.
Alternate Consideration
As directed by City Council.
Decision Mode
This item will be placed on the April 16, 2012 City
Council agenda for formal approval.