A resolution authorizing the purchase
of one (1) new Asphalt Box Trailer from Bonnell
Industries, Inc. in the amount of $17,945.00.
The
proposed asphalt trailer would be replacing a 1998 asphalt unit. The unit would
be utilized for hot and cold asphalt pot hole patching throughout the year.
Below
please find a summary of the three sealed bids received on July 19, 2010 for
the purchase of the Asphalt Box Trailer.
|
VENDOR |
MODEL DESCRIPTION |
PRICE
QUOTED |
|
Asphalt Maintenance & Construction |
KM International Inc Model KM 4000TEDX |
$25,127.60 |
|
Stepp
Manufacturing Co. |
STEPP SPH 1.5 |
$20,116.00 |
|
Bonnell Industries Inc |
Spaulding 2T Road Saver |
$17,945.00 |
The current budget included
funds for the proposed equipment and would be expensed from the following
line account:
|
ACCOUNT NUMBER |
ACCOUNT
DESCRIPTION |
FY 10/11
BUDGET |
PROPOSED
EXPENDITURE |
PROPOSED
BALANCE |
|
01-30-4815 |
EQUIPMENT-ASPHALT
BOX WITH TRAILER |
$22,260.00 |
$
17,945.00 |
$ 4,315.00 |
The Municipal Services Committee recommends
approval of the resolution authorizing the purchase one (1) new Asphalt Box
Trailer from Bonnell Industries, Inc. in the amount
of $17,945.00.