AGENDA MEMO
City Council
June 21, 2010
A resolution authorizing the
Mayor and City Clerk to execute a contract with North Suburban Asphalt Maintenance. in an amount not to
exceed $35,000.00 for the 2010 Crack Fill Program.
The FY 10/11 Budget includes $49,500.00 for the 2010 Crack Fill Program. Crack sealing is a routine maintenance treatment that will significantly delay roadway deterioration. The sealing material is applied into the cracks before they become too large and before the freeze-thaw cycles have an opportunity to shift the pavement and develop larger cracks (alligatoring). Flexible rubberized asphalt sealants bond to crack walls and move with the pavement, preventing water from entering the road base. The life of the road is extended and maintenance costs greatly reduced over time.
The scope of the program includes all cracks to be routed with a low dust mechanical router to a depth of ¾” and a width of ¾”. Upon completion of the routing, all dirt, debris, and water shall be removed from the cracks. The method of removal is completed by utilizing a blow pipe which blows compressed air from a pull behind conventional air compressor. The crack is then filled with a rubber sealant which is feathered to a width of approximately 3-inches in width. Attachment 1 is the proposed roads and field verified quantities for the program.
Sealed bids were opened on June 17, 2010 at the Darien City Hall. Staff had received 3 competitive bids for the Crack Sealing Program. Attached, please find a bid tally labeled as “Attachment 2” and below please find the results of the vendors. Staff is requesting a $5,000.00 contingency in the event additional cracks are identified in the field.
|
VENDOR |
BID RESULTS |
BID RESULTS WITH
$5,000 CONTINGENCY |
|
North Suburban
Asphalt Maintenance |
$30,000.00 |
$35,000.00 |
|
Rose Paving |
$86,500.00 |
$91,250.00 |
|
SKC Construction |
$38,250.00 |
$43,250.00 |
The
proposed Crack Sealing Program would be funded from the following FY10-11
Budget:
|
ACCOUNT NUMBER |
ACCOUNT
DESCRIPTION |
FY 10-11 BUDGET |
YEAR TO DATE TO
BE EXPENDED |
PROPOSED
EXPENDITURE |
PROPOSED BALANCE |
|
25-30-4382 |
CRACK FILL PROGRAM |
$49,500.00 |
-0- |
$ 30,000.00 |
$ 19,500.00 |
|
25-30-4382 |
CRACK FILL CONTINGENCY |
$49,500.00 |
$30,000.00 |
$ 5,000.00 |
$ 14,500.00 |
Staff recommends approval of the proposed motion. In anticipation of no July 5, 2010 meeting, this item will be placed under New Business for the June 21, 2010 City Council Meeting. The proposed vendor, North Suburban Asphalt Maintenance has provided services for the City of Darien in 2009 with satisfactory results.
As directed by the Municipal Services Committee.