AGENDA MEMO

City Council

June 21, 2010

ISSUE STATEMENT

A resolution authorizing the Mayor and City Clerk to execute a contract with North Suburban Asphalt Maintenance. in an amount not to exceed $35,000.00 for the 2010 Crack Fill Program.

 

RESOLUTION

BACKGROUND/HISTORY

The FY 10/11 Budget includes $49,500.00 for the 2010 Crack Fill Program. Crack sealing is a routine maintenance treatment that will significantly delay roadway deterioration. The sealing material is applied into the cracks before they become too large and before the freeze-thaw cycles have an opportunity to shift the pavement and develop larger cracks (alligatoring). Flexible rubberized asphalt sealants bond to crack walls and move with the pavement, preventing water from entering the road base. The life of the road is extended and maintenance costs greatly reduced over time.

 

The scope of the program includes all cracks to be routed with a low dust mechanical router to a depth of ¾” and a width of ¾”.  Upon completion of the routing, all dirt, debris, and water shall be removed from the cracks.  The method of removal is completed by utilizing a blow pipe which blows compressed air from a pull behind conventional air compressor. The crack is then filled with a rubber sealant which is feathered to a width of approximately 3-inches in width. Attachment 1 is the proposed roads and field verified quantities for the program.

 

Sealed bids were opened on June 17, 2010 at the Darien City Hall. Staff had received 3 competitive bids for the Crack Sealing Program.   Attached, please find a bid tally labeled as “Attachment 2” and below please find the results of the vendors. Staff is requesting a $5,000.00 contingency in the event additional cracks are identified in the field.

 

VENDOR

BID RESULTS

BID RESULTS WITH $5,000 CONTINGENCY

North Suburban Asphalt Maintenance

$30,000.00

$35,000.00

Rose Paving

$86,500.00

$91,250.00

SKC Construction

$38,250.00

$43,250.00

 

The proposed Crack Sealing Program would be funded from the following FY10-11 Budget:

 

ACCOUNT NUMBER

ACCOUNT DESCRIPTION

FY 10-11 BUDGET

YEAR TO DATE TO BE EXPENDED

PROPOSED EXPENDITURE

PROPOSED BALANCE

25-30-4382

CRACK FILL PROGRAM

 $49,500.00

-0-

 $      30,000.00

 $  19,500.00   

25-30-4382

CRACK FILL CONTINGENCY

$49,500.00

$30,000.00

 $        5,000.00

 $  14,500.00

 

STAFF RECOMMENDATION

Staff recommends approval of the proposed motion. In anticipation of no July 5, 2010 meeting, this item will be placed under New Business for the June 21, 2010 City Council Meeting.  The proposed vendor, North Suburban Asphalt Maintenance has provided services for the City of Darien in 2009 with satisfactory results.

ALTERNATE CONSIDERATION

As directed by the Municipal Services Committee.

DECISION MODE

This item will be placed on the June 21, 2010 agenda for formal consideration by the City Council.