AGENDA MEMO

City Council

February 16, 2010

ISSUE STATEMENT

Consideration of a motion to approve expenditure in the amount of $13,383 for the emergency restoration of the Tara Hill berm adjacent to Donegal Drive.   

 

2008 AERIAL

BACKGROUND/HISTORY

A special service area exists in the Tara Hill subdivision. Those residents pay a special property tax that is used for the maintenance of 3 detention basins in the Tara Hill subdivision which are owned by the City.

 

During October 2009 the City experienced a total rainfall of approximately 5.5 inches. On October 30, 2009, Staff was called out to inspect the Tara Hill detention basin adjacent to Donegal Drive. During our inspection we observed three areas where storm water was overflowing the detention basin causing flooding in the area adjacent to the basin. Staff identified a blockage in the pipe as a major cause of the poor drainage. However, Staff was also concerned since it appeared the basin was not operating as it was designed to do.  Due to the banks of the detention facility overflowing the City Engineer was directed to perform a topographic survey of the existing conditions and compare those to the original design plan. The topographic survey revealed that the banks were lower then the design plan resulting in water overflowing at the wrong place. Working with our City Engineer, he recommended a plan to correct the basin problem. The plan included raising the low spots and re-ditching the correct water overflow route. On January 7, 2010 Staff approved a competitive quote for the excavating equipment and operators on a per hour basis in an amount of $4,788.00. The final amount of our hours exceeded our initial estimate resulting in a total excavating cost of $6,583.  The City Engineer has verified the cuts and fills have been restored in accordance with the design plans. The total project cost is estimated at $15,383 which includes:

TASK                                                                    STATUS                     COST

Burke Engineering, topographical and staking           Completed                 $2,500

Excavating equipment and operators-                      Completed                  $6,583                        

Stone for storm water outlet structure                      February                     $1,000       

Burke- finished elevation grades and provide plan    In Process                   $1,800

Restoration to basin                                                April                            $1,500

      TOTAL-----------------------------------------------------------------------------------$13,383                                                                                           

This project was done on an emergency basis and in separate stages. However, the excavating/operator cost exceeded $5,000 so staff is asking for formal approval by the Council. This repair is estimated to reduce the fund balance in SSA to approximately $800.

STAFF RECOMMENDATION

Administrative/Finance Committee and Staff recommend approval of the expenditure in the amount $13,383 from the Tara Hill SSA fund for the emergency restoration of the Tara Hill berm adjacent to Donegal Drive.

ALTERNATE CONSIDERATION

No alternate consideration as project was completed on an emergency basis

DECISION MODE

This item will be placed on the February 16, 2010 City Council agenda for formal consideration.